Rule Change: RC_2008_09

A Rule Change Proposal made by Griffin Energy on 20 February 2008
Last updated:

Type: Fast Track Rule Change Process

Submitter: Griffin Energy

Title: NTDL new and Overnight Loads

Market Rules Affected: 4.28.9 and Appendix 5 (amended). Appendix 5A (new)

Date Submitted: 20 February 2008

Date First Published on the IMO Website: 29 February 2008

Date Final Report Published: 02 April 2008

Current Status: Closed. The Amending Rules commenced at 08.00am on 1 May 2008

Event Date Comments
Proposal Received by IMO 20/02/2008  
Notification Published 29/02/2008  
Requests to be Consulted 10/03/2008 The last date a Rule Participant can contact the IMO requesting to be consulted on the change.
Consultation Period 04/03/2008 – 26/03/2008 Must be completed within 15 B-Days from the date the notification is published
Final Report Published 02/04/2008 Must be published within 20 B-Days from the date the notification is published
Rule Commencement 01/05/2008