Rule Change: RC_2009_17

A Rule Change Proposal made by the Independent Market Operator on 5 May 2009
Last updated:

Type: Standard Rule Change Process

Submitter: IMO

Title: Transparency of Capacity Credit Allocation

Market Rules Affected: Clause 10.5.1(f)(iv)

Date Submitted: 05 May 2009

Date First Published on the IMO Website: 07 May 2009

Current Status: The Amending Rules commenced 1 March 2010

Event Date Comments
Notification Published 07/05/2009  
First Submission period 08/05/2009 – 19/06/2009 The submission period is 6 weeks from the date the IMO published the notification
Draft Report published 17/07/2009 Must be published within 20 B-Days after the end of the submission period
Second submission period 20/07/2009 – 21/08/2009 The submission period is 20 B-Days from the date the IMO published the Draft Report
Final Report Published 18/09/2009 Must be published within 20 B-Days after the end of the second submission period
Rule Commencement 01/03/2010