Rule Change: RC_2010_24

A Rule Change Proposal made by Alinta on 3 August 2010
Last updated:

Type: Standard Rule Change Proposal

Submitter: Alinta

Title: Adjustment of Relevant Level for Intermittent Generation Capacity

Market Rules Affected: Clauses 4.11.3A, 7.13.1C (new), 7.7.5B and 7.7.5E (new)

Date Submitted: 03 August 2010

Date First Published on the IMO Website: 09 August 2010

Current Status: The Amending Rules commenced on 1 July 2011

Event Date Comments
Notification Published 09/08/2010  
First Submission Period 10/08/2010 - 20/09/2010 The submission period is 30 B-Days from the date the IMO published the Draft Report
Draft Report Published 18/10/2010 Must be published within 20 B-Days of the end of the first submission period
Second Submission Period 19/10/2010 - 20/01/2010 The submission period has been extended. An extension notice was published on 18 October 2010
Final Report Published 01/04/2011 The timeframe for preparing the Final Rule Change Report was extended in accordance with the extension notice published 18 October 2010
Commencement 01/07/2011 Please note that this date is provisional and may be subject to change in the Final Rule Change Report