Rule Change: RC_2012_02

A Rule Change Proposal made by EnerNOC on 23 August 2012
Last updated:

Type: Standard Rule Change Process

Submitter: EnerNOC

Title: Relevant Demand of a Demand Side Program

Market Rules Affected: Clause 4.26.2CA

Date Submitted: 23 August 2012

Current Status: Closed

Event Date Comments
Notification Published 03/09/2012  
First Submission Period 04/09/2012 - 16/10/2012 The submission period is 30 B-Days from the date the IMO published the Rule Change Notice
Draft Report Published 22/05/2013 The timeframe for preparing the Draft Rule Change Report was further extended in accordance with the Extension Notice published on 15 May 2013
Second Submission Published 23/05/2013 - 20/06/2013 The submission period is at least 20 B-Days from the date the IMO publishes the Draft Rule Change Report
Final Report Published 18/07/2013 Must be published within 20 B-Days after the end of the second submission period
Commencement Not applicable The Rule Change Proposal was rejected by the IMO