Type: Standard Rule Change Process
Submitter: IMO
Title: Consideration of Network Constraints for Certified Reserve Capacity
Market Rules Affected: Clause 4.11.1
Date Submitted: 21 January 2013
Current Status: The Amending Rules commenced on 1 July 2013
| Event | Date | Comments |
|---|---|---|
| Notification Published | 21/01/2013 | |
| First Submission Period | 22/01/2013 - 06/03/2013 | The submission period is 30 B-Days from the date the IMO published the Rule Change Notice |
| Draft Report Published | 12/04/2013 | The timeframe for preparing the Draft Rule Change Report has been extended in accordance with the Extension Notice published on 5 April 2013. |
| Second Submission Period | 15/04/2013 - 13/05/2013 | The submission period is at least 20 B-Days from the date the IMO publishes the Draft Rule Change Report. |
| Final Report Published | 11/06/2013 | Must be published within 20 B-Days after the end of the second submission period. |
| Commencement | 01/07/2013 |