Rule Change: RC_2013_09

A Rule Change Proposal made by the Independent Market Operator on 18 June 2013
Last updated:

Type: Standard Rule Change Process

Submitter: Independent Market Operator (IMO)

Title: Incentives to Improve Availability of Scheduled Generators

Market Rules Affected: Clauses 2.17.1, 4.9.9, 4.11.1, 4.11.1A (new), 4.11.1B (new), 4.11.1C (new), 4.11.1D (new), 4.11.1E (new), 4.12.6, 4.12.9 (new), 4.12.10 (new), 4.26.1A, 4.26.2, 4.27.2A (new), 4.27.3, 4.27.3A (new), 4.27.3B (new), 4.27.4, 4.27.4A (new), 4.27.5, 4.27.6, 4.27.7, 4.27.8, 4.27.9 and the Glossary

Date Submitted: 18 June 2013

Current Status: Closed

Event Date Comments
Notification Published 18/06/2013  
First Submission Period 19/06/2013 - 27/08/2013 The timeframe for the first submission period was extended in accordance with the Extension Notice published on 9 August 2013
Draft Report Published 28/11/2013 The timeframe for preparing the Draft Rule Change Report was extended in accordance with the Extension Notices published on 18 June 2013, 9 October 2013 and 6 November 2013
Second Submission Published 29/11/2013 - 14/02/2014 The timeframe for the second submission period was extended in accordance with the Extension Notices published on 18 June 2013, 9 October 2013, 6 November 2013 and 13 January 2014
Final Report Published 24/03/2014 The timeframe for preparing the Final Rule Change Report was extended in accordance with the Extension Notices published on 18 June 2013, 9 October 2013, 6 November 2013 and 13 January 2014
Ministerial Approval By 21/05/2014 The timeframe for Ministerial Approval was extended in accordance with the Public Notice of the Extension of the Timeframe for Ministerial Approval published on 22 April 2014
Commencement Not applicable Not Applicable On 19 May 2014 the Minister notified the IMO of his decision to not approve the proposed Amending Rules