Rule Change: RC_2014_03

A Rule Change Proposal made by the Independent Market Operator on 27 November 2014
Last updated:

Type: Standard Rule Change Proposal

Submitter: IMO

Title: Administrative Improvements to the Outage Process

Market Rules Affected: 3.18.1A, 3.18.2A, 3.18.4A, 3.18.9A, 3.19.2E, 3.21.1, 3.21.2, 3.21.2B (new), 3.21.3, 3.21.4, 3.21.4A (new), 3.21.4B (new), 3.21.5, 3.21.6, 3.21.6A (new), 3.21.6B (new), 3.21.7 to 3.21.12, 3.21.13 to 3.21.17 (new), 4.11.1, 4.12.6, 4.25.3A, 4.25.9, 4.26.1, 4.26.1A, 4.26.1C, 4.26.2, 4.26.6, 6.3A.2, 6.3A.3, 6.15.2, 6.15.3, 6.17.5A, 6.17.9, 6.17.10, 7.3.4, 7.3.5, 7.10.2, 7.13.1A, 7.13.1D, 7.13.1E, 7.13.1F, 7.13.1G, 7A.2.4A, 7A.2.8A, 7A.2.8B (new), 7A.2.10, 7A.2A.1, 7A.2A.2, the Glossary and Appendix 9.

Date Submitted: 27 November 2014

Current Status: The Amending Rules commenced at 8:00 AM on 29 June 2021.

Event Date Comments
Notification Published 27/11/2014  
First Submission Period 28/11/2014 - 30/01/2015 The submission period has been extended 42 B-Days from the date the IMO published the Rule Change Notice.
Further Submission Period 06/01/2020 - 31/01/2020 A call for further submissions was published on 6 January 2020.
Draft Report Published 30/10/2020 The timeframe for publishing the Draft Rule Change Report was extended in accordance with the Extension Notice published on 30 June 2020.
Second Submission Period 30/10/2020 to 11/12/2020 The submission period was extended in accordance with the Extension Notice published on 2 December 2020.
Final Report Published 26/02/2021 The timeframe for publishing the Final Rule Change Report was extended in accordance with the Extension Notice published on 20 January 2021.
Commencement 29/06/2021  

 

Submissions received during the first submission period

Submissions received out of session

Submissions received in the second submission period

Submissions received after the second submission period