Rule Change: RC_2015_03

A Rule Change Proposal made by the Independent Market Operator on 27 March 2015
Last updated:

Type: Standard Rule Change Proposal

Submitter: IMO

Title: Formalisation of the Process for Maintenance Applications

Market Rules Affected: Clauses 2.24.1, 4.26.2C, 4.26.2CA, 4.26.2CB (new), 4.26.2CC (new), 4.26.2CD (new), 4.28.8, 4.28.9A (new), 4.28.9B (new), 4.28.9C (new), 4.28.9D (new), 4.28.9E (new), the Glossary and Appendix 5A.

Date Submitted: 27 March 2015

Current Status: The Amending Rules commenced at 8:00 AM on 1 October 2019.

Event Date Comments
Notification Published 27/03/2015  
First Submission Period 30/03/2015 - 13/05/2015 The submission period is at least 30 B-Days from the date the IMO published the Rule Change Notice.
Further Submission Period 24/10/2018 – 13/11/2018 A call for further submissions was published on 23 October 2018.
Draft Report Published 29/03/2019 The timeframe for publishing the Draft Rule Change Report was further extended in accordance with the Extension Notice published on 20 December 2018.
Second Submission Period 29/03/2019 - 01/05/2019 The submission period is at least 20 B-Days from the date the Rule Change Panel published the Draft Rule Change Report.
Final Report Published 25/06/2019 Must be published within 20 B-Days after the end of the second submission period.
Ministerial Approval 23/07/2019  
Commencement 01/10/2019