Type: Standard Rule Change Process
Submitter: Public Utilities Office
Title: Removal of constrained off compensation for Outages of network equipment
Market Rules Affected: 7.7.3A, 7.7.6, 7.7.7B (new), 7.7.11 (new), and Chapter 11 (Glossary)
Date Submitted: 14 December 2018
Current Status: The Amending Rules commenced at 8:00 AM on 1 July 2019.
| Event | Date | Comments |
|---|---|---|
| Notification Published | 17/12/2018 | |
| First Submission Period | 17/12/2018 - 08/02/2019 | The timeframe for the close of the First Submission period was extended beyond the usual 30 B-Days in accordance with the Rule Change Notice. |
| Draft Rule Change Report Published | 27/02/2019 | The Draft Rule Change Report must be published within 20 B-Days after the end of the first submission period. |
| Second Submission Period | 27/02/2019 - 28/03/2019 | The submission period is at least 20 B-Days from the publication of the Draft Report. |
| Final Rule Change Report Published | 30/04/2019 | The Final Rule Change Report must be published within 20 B-Days after the end of the second submission period. |
| Commencement | 01/07/2019 |