Rule Change RC_2019_01

An active Rule Change Proposal made by Enel X on 21 June 2019.
Last updated:

Type: Standard Rule Change Process.

Submitter: Enel X.

Title: The Relevant Demand calculation.

Market Rules Affected: 4.11.1(j) and Appendix 10.

Date Submitted: 21 June 2019.

Current Status: Closed.

Event Date Comments
Notification Published 28/06/2019  
First Submission Period 28/06/2019 - 09/08/2019 The submission period is at least 30 B-Days from the publication of the Rule Change Notice.
Draft Rule Change Report Published 21/09/2023 The timeframe for publishing the Draft Rule Change Report was extended in accordance with the Extension Notice published on 30 June 2023.
Second Submission Period 21/09/2023 - 20/10/2023 The submission period is at least 20 B-Days from the publication of the Draft Report.
Final Rule Change Report Published 9/11/2023 The Final Rule Change Report must be published within 20 B-Days after the end of the second submission period. The Coordinator rejected the Rule Change Proposal. 
Commencement NA The Coordinator rejected the Rule Change Proposal.