Type: Standard Rule Change Process
Submitter: Tesla Holdings Pty Ltd
Title: Release of Reserve Capacity Security once Reserve Capacity Obligations commence
Date Submitted: 2 November 2026
Current Status: The First submission period is open until 5pm (AWST) 21 December 2026
Event | Date | Comments |
Notification Published | 09/11/2026 |
|
First Submission Period | 09/11/2026 – 21/12/2026 | The submission period is 30 B-Days from the publication of the Rule Change Notice |
Draft Rule Change Report Published | 21/01/2027 | The Draft Rule Change Report must be published within 20 B-Days after the end of the first submission period. |
Second Submission Period | 21/01/2027 – 19/02/2027 | The submission period is at least 20 B‑Days from the publication of the Draft Rule Change Report. |
Final Rule Change Report Published | 22/03/2027 | The Final Rule Change Report must be published within 20 B-Days after the end of the second submission period.
|
Minister Approval | NA |
|
Commencement | TBC |
|