Clearing permit applications received are available for public submissions and/or registrations of interest. Clearing Permit decisions made are available for public appeal.
Submissions or Appeals are to be made within the time period specified in the advertisement.
New applications
| Clearing permit system link | CPS 11741/1 |
|---|---|
| Related documents | 11741/1 |
| Applicant | Carnegie Gold Pty Ltd |
| Project | Golden Eagle TSF Expansion |
| Permit type | Purpose Permit |
| Tenure | Mining Lease 30/255 |
| Shire | Shire of Menzies |
| Clearing purpose | Mineral production and associated activities |
| Size (ha) | 160.8 ha |
| Submission closing date | 30/10/2026 |
| Clearing permit system link | CPS 11755/1 |
|---|---|
| Related documents | 11755/1 |
| Applicant | Redstone Resources Limited |
| Project | |
| Permit type | Purpose Permit |
| Tenure | Exploration Licences 69/2450, 69/3456 |
| Shire | Shire of Ngaanyatjarraku |
| Clearing purpose | Mineral exploration and associated activities |
| Size (ha) | 6.1 ha |
| Submission closing date | 30/10/2026 |
| Clearing permit system link | CPS 11780/1 |
|---|---|
| Related documents | 11780/1 |
| Applicant | Geoda Pty Ltd & Lamerton Pty Ltd |
| Project | Lady Ida |
| Permit type | Purpose Permit |
| Tenure | Mining Leases 16/262, 16/263, 16/264, Miscellaneous Licences 16/58, 16/62, 16/103 |
| Shire | Shire of Coolgardie |
| Clearing purpose | Mining operations |
| Size (ha) | 400 ha |
| Submission closing date | 23/10/2026 |
| Clearing permit system link | CPS 11588/1 |
|---|---|
| Related documents | 11588/1 |
| Applicant | MEPAU Perth Basin Pty Ltd |
| Project | Woodada Gas Field |
| Permit type | Purpose Permit |
| Tenure | Production Licence L4 R1 |
| Shire | Shire of Carnamah |
| Clearing purpose | Decommissioning and rehabilitation activities |
| Size (ha) | 2.82 ha |
| Submission closing date | 21/10/2026 |
Submissions for Applications for clearing permits are to be made within the time frame specified in the Advertising Closing Date.
Documents relating to clearing permit applications or decisions can be accessed via the FTP website: https://ftp.dwer.wa.gov.au/permit/. Please note: This website can only be accessed via the Microsoft Edge browser or Internet Explorer.
If you would like to be notified of Notifications of Clearing Permit Applications and decisions subscribe here.
Submissions may be forwarded to Resource and Environmental Compliance Division, Department of Mines, Petroleum, and Exploration, 100 Plain St, EAST PERTH WA 6004 or email: nvab@dmpe.wa.gov.au.
Amendment applications
| Clearing permit system link | CPS 11483/2 |
|---|---|
| Related documents | 11483/2 |
| Applicant | Northern Star Resources Ltd |
| Project | Jundee Sitewide Clearing Permit |
| Permit type | Purpose permit |
| Tenure | General Purpose Lease 53/20, Mining Leases 53/191, 53/412, 53/413, 53/414, 53/461, 53/552 |
| Shire | Shire of Wiluna |
| Clearing purpose | Mineral extraction and associated activities |
| Size (ha) | 500 ha |
| Amendment requested | Amendment to correct clerical error |
| Submission closing date | 20/10/2026 |
Submissions for Applications for amendments to clearing permits are to be made within the time frame specified in the Advertising Closing Date.
Documents relating to clearing permit applications or decisions can be accessed via the FTP website: https://ftp.dwer.wa.gov.au/permit/. Please note: This website can only be accessed via the Microsoft Edge browser or Internet Explorer.
If you would like to be notified of Notifications of Clearing Permit Applications and decisions subscribe here.
Submissions may be forwarded to Resource and Environmental Compliance Division, Department of Mines, Petroleum, and Exploration, 100 Plain St, EAST PERTH WA 6004 or email: nvab@dmpe.wa.gov.au.
Clearing decisions made for public appeal
| Clearing permit system link | CPS 11375/1 |
|---|---|
| Related documents | 11375/1 |
| Permit holder & project | North West Quarries Pty Ltd - Red Hill Sand Quarry |
| Permit Type | Purpose permit |
| Tenure | Mining Lease 47/1495 |
| Shire | Town of Port Hedland and City of Karratha |
| Clearing purpose | Sand mining and associated activities |
| Size (ha) | 85 ha |
| Permit duration | 12 November 2026 – 11 November 2034 |
| Decision date | 20/10/2026 |
| Appeals closing date | 10/11/2026 |
| Clearing permit system link | CPS 11708/1 |
|---|---|
| Related documents | 11708/1 |
| Permit holder & project | Cygnet Gold Pty Ltd - Golden Pig |
| Permit Type | Purpose permit |
| Tenure | Mining Leases 77/109, 77/535, 77/552, 77/1016 |
| Shire | Shire of Yilgarn |
| Clearing purpose | Dewatering pipeline |
| Size (ha) | 3.0 ha |
| Permit duration | 12 November 2026 – 11 November 2031 |
| Decision date | 20/10/2026 |
| Appeals closing date | 10/11/2026 |
| Clearing permit system link | CPS 9302/2 |
|---|---|
| Related documents | 9302/2 |
| Permit holder & project | Bardoc Gold Pty Ltd Scotia - Borefield Recommissioning Project |
| Permit Type | Purpose Permit |
| Tenure | Miscellaneous Licences 24/148, 24/202, 24/203 |
| Shire | City of Kalgoorlie-Boulder |
| Clearing purpose | Recommissioning a borefield |
| Size (ha) | 43.5 ha |
| Permit duration | 16 October 2021 - 15 October 2031 |
| Decision date | 15/10/2026 |
| Appeals closing date | 05/11/2026 |
| Clearing permit system link | CPS 11194/1 |
|---|---|
| Related documents | 11194/1 |
| Permit holder & project | Navigator Mining Pty Ltd - East Cardinia Gold Project |
| Permit Type | Purpose Permit |
| Tenure | Mining Lease 37/316 |
| Shire | Shire of Leonora |
| Clearing purpose | Mining infrastructure |
| Size (ha) | 89.35 ha |
| Permit duration | 5 November 2026 – 4 November 2031 |
| Decision date | 13/10/2026 |
| Appeals closing date | 03/11/2026 |
| Clearing permit system link | CPS 11031/2 |
|---|---|
| Related documents | 11031/2 |
| Permit holder & project | Process Minerals International Pty Ltd - Lamb Creek Project |
| Permit Type | Purpose Permit |
| Tenure | Mining Lease 47/1592, Miscellaneous Licence 47/1008 |
| Shire | Shire of East Pilbara |
| Clearing purpose | Mineral production and associated activities |
| Size (ha) | 638.4 ha |
| Permit duration | 11 November 2025 - 10 November 2033 |
| Decision date | 08/10/2026 |
| Appeals closing date | 29/10/2026 |
| Clearing permit system link | CPS 9337/3 |
|---|---|
| Related documents | 9337/3 |
| Permit holder & project | APA Operations (WA) Pty Ltd - King of the Hills Gas Pipeline |
| Permit Type | Purpose Permit |
| Tenure | Petroleum Pipeline Licence 126, Miscellaneous Licence 37/248 |
| Shire | Shire of Leonora |
| Clearing purpose | Gas pipeline |
| Size (ha) | 80 ha |
| Permit duration | 9 October 2021 – 8 October 2031 |
| Decision date | 06/10/2026 |
| Appeals closing date | 27/10/2026 |
| Clearing permit system link | CPS 11093/3 |
|---|---|
| Related documents | 11093/3 |
| Permit holder & project | Mt Magnet Gold Pty Ltd - Mount Magnet Project |
| Permit Type | Purpose Permit |
| Tenure | Mining Leases 58/30, 58/60, 58/78, 58/79, 58/80, 58/81, 58/119, 58/120, 58/121, 58/136, 58/147, 58/173, 58/174, 58/180, 58/186, 58/187, 58/192, 58/193, 58/194, 58/201, 58/205, 58/210, 58/233, 58/273, 58/375 General Purpose Lease 58/8 |
| Shire | Shire of Mount Magnet |
| Clearing purpose | Mineral production and associated activities |
| Size (ha) | 950 ha |
| Permit duration | 27 November 2025 – 26 November 2030 |
| Decision date | 01/10/2026 |
| Appeals closing date | 22/10/2026 |
| Clearing permit system link | CPS 11745/1 |
|---|---|
| Related documents | 11745/1 |
| Permit holder & project | Norwest Sand & Gravel Pty Ltd - Turner River Pindan Sand |
| Permit Type | Purpose Permit |
| Tenure | Mining Lease 45/1195 |
| Shire | Town of Port Hedland |
| Clearing purpose | Sand mining and associated activities |
| Size (ha) | 25 ha |
| Permit duration | 27 October 2026 –26 October 2031 |
| Decision date | 02/10/2026 |
| Appeals closing date | 23/10/2026 |
| Clearing permit system link | CPS 11582/1 |
|---|---|
| Related documents | 11582/1 |
| Permit holder & project | Genesis Minerals (Leonora) Pty Ltd - Tower Hill Stage 2 Project |
| Permit Type | Purpose Permit |
| Tenure | Mining Lease 37/25, 37/55, 37/251, 37/622, 37/689, Miscellaneous Licences 37/263, 37/290 |
| Shire | Shire of Leonora |
| Clearing purpose | Mineral production |
| Size (ha) | 122.44 ha |
| Permit duration | 23 October 2026 to 22 October 2031 |
| Decision date | 30/09/2026 |
| Appeals closing date | 21/10/2026 |
Appeals against a grant of a clearing permit, appeals against the refusal to grant a permit, refusal to permit all clearing; an amendment, revocation or suspension of a clearing permit; or the conditions of permit must be made within 21 days of the applicant receiving notification of the decision.
Documents relating to clearing permit applications or decisions can be accessed via the FTP website: https://ftp.dwer.wa.gov.au/permit/. Please note: This website can only be accessed via the Microsoft Edge browser or Internet Explorer.
If you would like to be notified of Notifications of Clearing Permit Applications and decisions subscribe here.
Appeals may be lodged online with the Appeals Convenor. For further information about lodging or the appeals process, please visit www.appealsconvenor.wa.gov.au. If you have any queries, please contact the Office of the Appeals Convenor on (08) 6364 7990 or email to admin@appealsconvenor.wa.gov.au
All matters not for public comment or appeal
Clearing Referrals - Not for public comment or appeal
Clearing Referrals proposed under Section 51DA(2) and decision of clearing referrals under section 51 DA(3) of the Environmental Protection Act 1986 (EP Act)
No applications
Surrender Applications – Not for public comment or appeal
No applications
Application to surrender a clearing permit made under Section 51 MA(1) of the EP Act, and the acceptance or refusal of an application to surrender a clearing permit made under Section 51MA(7) of the EP Act.
Decision to revoke or suspend a clearing permit made under Section 51L (1) of the EP Act. Decision to refuse to grant a clearing permit under Section 51E(5)(b) of the EP Act.
Decision to amend a clearing permit under section 51 K(2)(b) - Not for public comment or appeal
Decision to amend a clearing permit under Section 51K(2)(b) of the EP Act on the initiative of the Chief Executive Officer (CEO). Amendment decisions that are not appealable include CEO-initiated amendments and amendments to give effect to a decision of the Minister for Environment.
No applications