Rule Change: RC_2007_10

A Rule Change Proposal made by Synergy on 13 September 2007
Last updated:

Submitter: Synergy

Title: Intermittent Generator Resource Plan Exemption

Market Rules Affected: 6.5.1A, 6.5.1C, 6.17.1, 6.17.5, 6.21.2, 7.10.1, 9.8.1 and the Glossary

Date Submitted: 13 September 2007

Date First Published on the IMO Website: 17 September 2007

Date Final Report Published: 17 January 2008

Current Status: Closed. The amendments to the Market Rules commenced on 1 February 2008

Event Date Comments
Proposal Received by IMO 13-09-2007  
Notification Published 17-09-2007  
First Submission period 17-09-2007 – 29-10-2007 The submission period is 6 weeks from the date the IMO published the notification
Draft Report published 26-11-2007 Must be published within 20 B-Days after the end of the submission period
Second submission period 26-11-2007 – 24-12-2007 The submission period is 20 B-Days from the date the IMO published the Draft Report
Final Report Published 17-01-2008 Must be published within 20 B-Days after the end of the second submission period
Rule Commencement 01-02-2008