Rule Change: RC_2010_01

A Rule Change Proposal made by Verve Energy on 12 February 2010
Last updated:

Type: Standard Rule Change Proposal

Submitter: Verve Energy

Title: Annual Review of Margin Values

Market Rules Affected: 3.13.3A

Date Submitted: 12 February 2010

Date First Published on the IMO Website: 15 February 2010

Current Status: The Amending Rules commenced at 8.00am on 1 July 2010

Event Date Comments
Notification Published 15/02/2010  
First Submission Period 16/02/2010 - 30/03/2010 The submission period is 30 B-Days from the date the IMO published the Draft Report
Draft Report Published 30/04/2010 Must be published within 20 B-Days of the end of the first submission period
Second Submission Period 30/04/2010 - 27/05/2010 The submission period is at least  20 B-Days from the date the IMO published the Draft Report
Final Report Published 25/06/2010 Must be published within 20 B-Days after the end of the second submission period
Commencement 1/07/2010