Rule Change: RC_2010_37

A Rule Change Proposal made by Griffin Energy on 30 November 2010
Last updated:

Type: Standard Rule Change Process

Submitter: Griffin Energy

Title: Calculation of the Capacity Value of Intermittent Generation – Methodology 2 (Griffin Energy)

Market Rules Affected: Clauses 4.11.3A, 7.7.5B, 7.7.5C, 7.7.5E, 7.13.1,10.5.1 and the Glossary

Date Submitted: 30 November 2010    

Current Status: Closed.

Event Date Comments
Notification Published 06/12/2010  
First Submission Period 07/12/2010 - 04/02/2011 The timeframe for the first submission period was extended in accordance with the Extension Notice published on 6 December 2010
Draft Report Published 18/08/2011 The timeframe for preparing the Draft Report was further extended in accordance with the Extension Notice published on 27 July 2011
Second Submission Published 19/08/2011 - 21/10/2011 The timeframe for the second submission period was further extended in accordance with the Extension Notice published on 13 October 2011 
Public workshop 08/09/2011 The IMO held a public workshop during the second submission period to present the analysis and recommendations of the Sapere report
Further Consultation Period 21/11/2011 - 30/11/2011 The IMO is providing interested parties with a further consultation period in accordance with the Extension Notice published on 21 November 2011
Final Report Published 20/12/2011 The Final Report was published after Board approval was given in session on 15 December 2011
Commencement Not Applicable This rule change was rejected by the IMO