Rule Change: RC_2012_16

A Rule Change Proposal made by the Independent Market Operator on 16 November 2012.
Last updated:

Type: Fast Track Rule Change Process

Submitter: IMO

Title: Alignment of Settlement Tolerances and Tolerance Ranges

Market Rules Affected: Clauses 2.13.6L (new) and 6.17.9

Date Submitted: 16 November 2012

Current Status: The Amending Rules commenced on 1 November 2013

Event  Date Comments
Notification Published 16/11/2012  
Requests to be Consulted 23/11/2012 The last date a Rule Participant can contact the IMO requesting to be consulted on the change.
Consultation Period 19/11/2012 - 07/12/2012 Must be completed within 15 B-Days from the date the notification is published.
Final Rule Change Report 14/12/2012 Must be published within 20 B-Days from the date the notification is published.
Ministerial Approval by 18/09/2013 The Final Rule Change Report was approved by the Minister on 17 September 2013. 
Commencement 01/11/2013