Rule Change: RC_2012_19

A Rule Change Proposal made by the Independent Market Operator on 16 November 2012
Last updated:

Type: Fast Track Rule Change Process

Submitter: IMO

Title: Constrained On/Off Compensation for Non-Scheduled Generators

Market Rules Affected: Clauses 6.16A.2 and 6.17.3A.

Date Submitted: 16 November 201

Current Status: The Amending Rules commenced on 1 February 2013

Event Date Comments
Notification Published 16/11/2012  
Requests to be Consulted 23/11/2012 The last date a Rule Participant can contact the IMO requesting to be consulted on the change
Consultation Period 19/11/2012 - 07/12/2012 Must be completed within 15 B-Days from the date the notification is published
Final Rule Change Report 09/01/2013 The publication date has been further extended in accordance with the Extension Notice published on 21 December 2012
Commencement 01/02/2013