Rule Change: RC_2013_15

A Rule Change Proposal made by the Independent Market Operator on 24 December 2013
Last updated:

Type: Standard Rule Change Proposal

Submitter: IMO

Title: Outage Planning Phase 2 - Outage Process Refinements

Market Rules Affected:  Clauses 3.18.1, 3.18.1A (new), 3.18.1B (new), 3.18.1C (new), 3.18.2, 3.18.2A, 3.18.3, 3.18.4, 3.18.4A, 3.18.5, 3.18.5C, 3.18.5D, 3.18.6, 3.18.6A (new), 3.18.7, 3.18.8, 3.18.9, 3.18.9A (new), 3.18.9B (new), 3.18.9C (new), 3.18.10, 3.18.10A (new), 3.18.10B (new), 3.18.11, 3.18.14, 3.18.15, 3.18.16, 3.19.1, 3.19.2, 3.19.2A (new), 3.19.2B (new), 3.19.2C (new), 3.19.2D (new), 3.19.2E (new), 3.19.2F (new), 3.19.2G (new), 3.19.2H (new), 3.19.3, 3.19.3A, 3.19.3B (new), 3.19.3C (new), 3.19.4A (new), 3.19.11, 3.19.12, 3.20.1, 3.21A.14, 7.1.1, 7A.2.4C, 7A.2.6, 7A.2.8A (new), 7A.2.9, 7A.2.9A (new), 7A.2.9B (new), 7A.2.9C (new), 7A.2A.1 (new), 7A.2A.2 (new), 7A.2A.3 (new), 7A.2A.4 (new) and the Glossary.

Date Submitted: 24 December 2013

Current Status: The Amending Rules commenced at 8:00 AM on 1 February 2020.

Event Date Comments
Notification Published 24/12/2013  
First Submission Period 27/12/2013 - 04/03/2014 The submission period has been extended to 45 B-Days from the date the IMO published the Rule Change Notice.
Further Submission Period  11/12/2018 - 11/01/2019   
Draft Report Published 16/05/2019 The timeframe for preparing the Draft Rule Change Report was further extended in accordance with the Extension Notice published on 25 March 2019.
Second Submission Period 16/05/2019 - 28/06/2019 The submission period is at least 20 B-Days from the date the Rule Change Panel published the Draft Report.
Final Report Published 26/08/2019 The timeframe for preparing the Final Rule Change Report has been further extended in accordance with the Extension Notice published on 16 May 2019.
Commencement 01/02/2020  

 

Submissions received out of session on the Rule Change Proposal