Rule Change: RC_2010_04

A Rule Change Proposal made by the Independent Market Operator on 7 April 2010
Last updated:

Type: Standard Rule Change Proposal

Submitter: IMO

Title: Settlement in Default Situations

Market Rules Affected: 6.16.1, 9.3.3, 9.24.3, 9.24.5 and 9.24.9

Date Submitted: 07 April 2010

Date First Published on the IMO Website: 07 April 2010

Current Status: The Amending Rules commenced at 8:00am 1 October 2010

Event Date Comments
Notification Published 07/04/2010  
First Submission Period 08/04/2010 - 20/05/2010 The submission period is 30 B-Days from the date the IMO published the Draft Report
Draft Report Published 26/07/2010 The timeframe for preparing the Draft Rule Change Report was extended in accordance with the notices of extension published 18 June 2010 and 16 July 2010
Second Submission Period 27/07/2010 - 23/08/2010 The submission period is at least  20 B-Days from the date the IMO published the Draft Report
Final Report Published 17/09/2010 Must be published within 20 B-Days after the end of the second submission period
Commencement 01/10/2010