The Department of Local Government, Industry Regulation and Safety (LGIRS) collects personal information for the purpose of:
- regulating health and safety of workers, at workplaces;
- regulating risks to health and safety arising from work and for related purposes;
- processing your application and verifying your eligibility;
- maintaining licence and registration records;
- undertaking compliance and enforcement activities;
- engagement and educational activities;
- other regulatory functions.
Your personal information is collected under the relevant provisions of the Work Health and Safety Act 2020.
If you do not provide the requested information, LGIRS may be unable to process your application or provide the relevant licence or service.
Your information may be included in an online licence search, published in a register, or disclosed where authorised or required by law. This may include to other government agencies, regulatory bodies, medical or technical experts, employers, trainers, and other third parties.
Please refer to the Privacy Policy on our website for more information about how we handle your personal information, how you can request access to or correction for the personal information we hold about you, and who to contact if you have a privacy enquiry or complaint.
When is a Demolition Licence Required?
A demolition licence is required for certain demolition work regulated by WorkSafe WA.
Class 1 Demolition Licence
Required for higher-risk demolition work, including:
- work comprising the total demolition or dismantling of a structure that is 10 metres or more in height when measured from the lowest ground level of the structure to the highest part of the structure;
- comprising the partial demolition or dismantling of a structure that is 10 metres or more in, height when measured from the lowest ground level of the structure to the highest part of
the structure; - comprising demolition work on a structure; and involving the use of load shifting equipment on a suspended floor;
- work comprising demolition work on pre-tensioned or post-tensioned structural components of a structure;
- work comprising demolition work on a structure containing precast concrete elements erected by the tilt-up method of construction;
- work involving the removal of key structural members of a structure so that the whole or a part of the structure collapses;
- work done to a structure involving explosives;
- work comprising demolition work on a structure that involves the use of a tower crane or any crane with a safe working load greater than 100 tonnes;
- work involving the removal of an area of brittle or fragile roofing material in excess of 200 m2 from a structure if any part of the area to be removed is 10 metres or more above the lowest ground level of the structure.
Class 2 demolition work
Is work comprising demolition work involving a structure that is less than 10 metres in height when measured from the lowest ground level of the structure to the
highest part of the structure, excluding:
- demolition work involving a single storey dwelling;
- demolition work on a structure; and involving the use of load shifting equipment on a suspended floor;
- demolition work on pre-tensioned or post-tensioned structural components of a structure; demolition work on a structure containing precast concrete elements erected by the tilt-up method of construction;
- work involving the removal of key structural members of a structure so that the whole or a part of the structure collapses;
- work done to a structure involving explosives;
- work comprising demolition work on a structure that involves the use of a tower crane or any crane with a safe working load greater than 100 tonnes.
Typical Class 2 projects may include:
- Small commercial buildings
- Low-rise industrial structures
- Warehouses and sheds
- Internal structural demolition
- Smaller-scale demolition projects
When is a Licence Not Required?
A demolition licence is generally not required for:
- A fence or wall less than 1.8 metres in height
- A structure less than 2 metres in height
- A structure by a person in the metal fabrication or engineering industry in the course of maintaining, refurbishing, upgrading, modifying or decommissioning plant.
- Demolition involving a single story dwelling - Regulation 142C (1) (a)
- the dismantling of formwork, falsework, scaffolding or other structures designed or used to provide support, access or containment during construction work, or
- the removal of power, light or telecommunication poles
Where demolition work other than Class 1 or Class 2 demolition work is carried out, the PCBU or principal contractor must ensure the work is carried out in accordance with AS 2601.
How to apply
Read the Applicant guide.
Step 1: Confirm Eligibility
Ensure you meet the licence and supervisor requirements.
Step 2: Nominate a Supervisor
Demolition licence holders can only engage one nominated supervisor at a time.
Every application must include a Nominated Supervisor (which can be you). Individual applicants may engage a different person as the nominated supervisor.
The nominated supervisor is responsible for overseeing demolition work and must demonstrate competency in safe demolition practices.
The nominated supervisor must provide:
- Proof of identification
- Evidence of competency of the below units issued by a Registered Training Organisation (RTO). Equivalent units may also be accepted.
- CPCCWHS2001 — Apply WHS requirements, policies and procedures
- CPCCCM2009 — Carry out basic demolition
- Recent demolition experience relevant to the licence class being applied for
- Experience must be a minimum of three (3) substantial jobs within the past 5 years, in the class for which you are applying. Note: Demolition jobs will be referenced against Demolition of Work Notifications submitted to the WorkSafe Commissioner under regulation 142F.
- Two written references by two separate referees confirming the experience listed on the Statement of Experience.
- Referees should:
- Have direct knowledge of the work completed, be independent and credible and be able to verify project details and responsibilities provided in the nominated supervisor experience
- Referees need to:
- explain of the referee’s relationship and the capacity to independently verify and endorse the nominated supervisor’s experience
- the type of work completed by the nominated supervisor i.e. occupation, duties, roles, and responsibilities;
- the start and finish date of each project the referee is verifying;
- verify the address of each demolition project listed on the Statement of Experience;
- Full name, email address, and telephone number of the referee.
- Sign and date the reference.
- Referees may be contacted by Licensing Services to verify your experience.
Step 3: Gather Supporting Documents
- Provide evidence of a safety Management Plan
- Must address all of the following management criteria in relation to the class of demolition work applied for:
- Planning
- Consultation
- Hazard management
- Training
- Must address all of the following management criteria in relation to the class of demolition work applied for:
- If using a business trading name, provide a business extract issued by the Australian Securities & Investments Commission (ASIC).
Step 4: Complete the application form
Complete all sections of the application form. Provide as much detail as possible. For further assistance completing this application consult the Application guide or contact us.
Step 5: Apply for your licence
Online
Apply and pay for your application
If you are not able to apply online, the following options are available:
| By Post | In Person |
|---|---|
If posting your application and Post to: Licensing Services | Visit: Customer Service |
Already have a licence in Australia or New Zealand?
Show moreIf you have a demolition licence elsewhere in Australia or New Zealand and want to carry out demolition work in Western Australia, you can
Definitions of Demolition work classes
Show moreA Demolition Licence is required for the demolition or dismantling of:
- a structure 2 metres or higher which is not a single storey dwelling; or
- a fence or wall 1.8 metres or higher.
The licence can be designated Class 1 or Class 2.
It is an offence to do any of the work described as Class 1 or Class 2 demolition work unless licensed to do the work.
| Class 1 | Class 1 demolition work is work:
|
| Class 2 | Class 2 demolition work is work comprising demolition work involving a structure that is less than 10 metres in height when measured from the lowest ground level of the structure to the highest part of the structure, excluding:
|
Fees
Show morePlease refer to the demolition licensing fees page for fees related to your licence.